Congestion at several major UAE ports is creating additional pressure on vessel schedules and container movements across the region. Longer waiting times at Khor Fakkan and Fujairah, combined with delays at Sharjah, are making cargo planning more difficult for shipping lines, freight forwarders, importers and exporters.
According to operational data published by Kuehne+Nagel on 30 October 2026, the disruption is affecting both vessel operations and the movement of containers between terminals and regional logistics hubs.
Vessel Waiting Times Increase at Key UAE Ports
The latest operational figures show significant delays at several UAE ports.
At Khor Fakkan, the average vessel waiting time reached 7.25 days. Over the preceding 30 days, vessels arrived an average of 7.4 days behind schedule and departed 5.7 days late.
At Fujairah, the average container vessel waiting time over a seven-day period reached 8.86 days. Average arrival delays were 7.58 days, while departures were delayed by 7.65 days.
In Sharjah, vessel waiting times were approximately three days, with average arrival and departure delays exceeding four days over the preceding 30 days.
These figures refer to different reporting periods and should not be treated as a direct like-for-like comparison. However, they indicate that congestion is affecting multiple locations along the UAE's eastern and northern port network.
Container Transfers Are Taking Longer
The disruption is also affecting the movement of containers between ports and terminals.
According to Kuehne+Nagel, transfers from Khor Fakkan and Fujairah to other UAE gateways, including Jebel Ali, Sharjah and Abu Dhabi, are taking approximately 12–15 days. Previously, similar movements could take around five days.
Longer transfer times can affect delivery planning, warehouse operations and onward transportation. Importers and exporters may need to allow additional time when arranging cargo collection and connecting shipments.
Carriers Adjust Booking Availability
Shipping lines are responding to the operational situation by adjusting booking availability for certain destinations.
On 30 October 2026, Maersk issued an advisory announcing temporary booking restrictions for Khor Fakkan, Fujairah and selected Upper Gulf destinations.
The restrictions do not mean that all cargo movements have stopped. The handling of existing bookings, cargo already in transit and new booking requests may differ depending on the destination and available capacity.
For shippers, this makes it important to confirm current booking conditions with their carriers before arranging new shipments.
Alternative Ports and Routing Options
When congestion affects a particular gateway, logistics providers may consider alternative ports and transportation routes.
Kuehne+Nagel has identified Salalah and Duqm as potential alternatives for some cargo flows. However, their suitability depends on the shipment's origin, final destination, carrier services and available inland transportation.
Changing a port of discharge can also introduce additional handling and transit time. Therefore, alternative routing should be evaluated on a shipment-by-shipment basis rather than treated as a universal solution.
Why Vessel Schedule Visibility Matters
When port operations become unpredictable, accurate vessel schedule information becomes especially important.
A delayed vessel can affect connecting services, container availability and planned delivery dates. Freight forwarders and cargo owners need to monitor schedule changes and reassess their logistics plans when new delays appear.
The Qubictron Vessel Schedules tool helps users check vessel schedules and plan shipments around available sailing information. Having access to schedule data can support better coordination between carriers, freight forwarders and cargo owners.
What Shippers Should Consider
With congestion affecting several UAE gateways, businesses moving cargo through the region should consider:
Allowing additional time for vessel arrivals and container transfers.
Confirming booking availability with carriers before shipping.
Monitoring schedule changes and revised estimated arrival times.
Evaluating alternative ports when the original gateway faces significant delays.
Coordinating port operations with inland transportation and warehouse availability.
Outlook: Continued Pressure on Regional Logistics
Kuehne+Nagel has warned that operational pressure may continue to affect cargo flows in the region. The actual impact will depend on port conditions, carrier capacity and how quickly vessel queues and container movements return to normal.
For businesses relying on UAE ports, the situation highlights the importance of flexible routing, realistic transit-time planning and continuous shipment monitoring.
As congestion develops, timely schedule information and alternative logistics options will remain important tools for managing uncertainty across regional supply chains.